The Problem: iEnvi supported a Tier 1 infrastructure contractor that was engaged to provide critical telecommunication (NBN) upgrades across [...]
- 03 February 2026
The Problem: A semi-rural property in north-west Sydney received imported fill that included construction and demolition waste. Asbestos-containing materials [...]
- 29 January 2026
The Problem: A proposed school site in Wollert, Victoria, required confirmation that past land uses, primarily agricultural activities, had [...]
- 18 September 2025
The Problem: A new flammable goods storage zone was planned at an industrial chemical site in Victoria. Excavation [...]
- 24 May 2024
The Victorian EPA requested an investigation at an industrial site in Coolaroo to meet General Environmental Duty requirements. iEnvironmental [...]
- 04 June 2020
When is a Soil Stockpile ‘Waste’, and Can a Hotspot of Asbestos or ACM in a Stockpile be Removed and [...]
- 09 August 2019
A major coal mining client engaged iEnvironmental Australia to undertake asbestos monitoring in accordance with an existing Asbestos Management Plan, [...]